Battery Storage

Advancing peak shaving and storage opportunities through a variety of facilities and capabilities is a GLEAMM priority.

Facilities and Equipment:

  • 1MW/1MWh Battery
    • DOE provided the funds to deploy a 1MW/1MWh battery to be used in coordination with the wind turbines at the site.
    • The battery works in concert with the load, wind turbines, and can be connected to any future development.
  • Primary test bed located at Reese Technology Center.

Team Leaders:

Experience:

  • The team performed long term testing on the performance of the 1MW/1MWh battery system which included the following types of test:
    • Ramp Rate Control;
    • Demand Shaving;
    • Frequency Response; and
    • Combinations of the above.